45/55 North Main Street Construction Update
From Steve King, Senior Project Manager, Groen Construction
Posted on: November 4, 2022 - 2:13pm
Construction activities for the next two weeks are as follows:
- On Monday, November 07, 2022, our site subcontractor will be in N Main starting our new utility connection work. Work in N Main will take about two weeks as we must excavate in five different locations for our new water, sanitary sewer, and storm drain.
- Also on Monday, we will place concrete for the foundation of the new building.
- We will continue to haul off-site sand and demolition debris to excavate to the correct elevations for the new foundations. Our return trips will be to import backfill material.