We are providing the following to be posted for upcoming construction activities.

From Steve King, Senior Project Manager, Groen Construction

Construction activities for the next two weeks are as follows:

  • We completed the last footing concrete placement this week on Wednesday, January 04, 2023
  • Our goal is to finish the ICF wall placements by Wednesday, January 11, 2023
  • We are continuing with installation of interior underground utilities
  • Interior backfill of the building footprint for slabs is progressing
  • During the week of January 16th, our steel erection sub will mobilize
  • The crane is scheduled to be set up in our staging area on Wednesday, January 18, 2023
  • Steel deliveries will commence also on Wednesday the 18th
  • Steel will be erected starting at the N Main Street front wall and will progress towards our staging area in the Union Street lot
  • Steel erection and slab placements for the six-story building should be completed around the middle of April