Construction Update: 45/55 North Main Street

For questions, call Matt Wyatt (603) 330-7195

From Steve King, Senior Project Manager, Groen Construction:

  • The steel erection crew has finished prefab walls and steel placement on the first floor
  • The crane has been pushed back from the building's north wall
  • Work is being completed to close up shear wall forms for the two stairs and elevator shaft
  • The concrete for shear walls is set for placement on Friday, March 10, 2023
  • Work continues to install plywood and wire mesh for the second-floor slab placement which should occur next week
  • Temporary protection work is ongoing to close up the front of the building at N Main
  • Installation of two temporary heaters is underway now to have heat running within the building to maintain temperature to place the concrete slab
  • Material deliveries for the second floor of the building are due on-site from Canada at the end of next week.