45/55 North Main Street Construction Update
From Steve King, Senior Project Manager, Groen Construction.
- Demolition of 45 N Main & 55 N Main is complete as of today.
- The demolition equipment will be demobilized and leave our staging area by Thursday.
- Survey and control layout work will be performed on Friday.
- Utility relocation work will be performed in our staging area for the next two weeks as we prepare to start concrete foundation work for the new building.