45/55 North Main Street Construction Update

Construction activities scheduled for the next two weeks are as follows:

  • Continue inside of 55 N Main with the abatement and hazmat removal work.
  • Obtain a permit to close off the public sidewalk in front of 45/55 N Main
  • Obtain a permit to close off three public parking spaces in N Main adjacent to 45/55 
  • Install Jersey concrete barriers in front of 45/55
  • Install chain link temporary fence at N Main per logistics plan
  • Remove the public sidewalk in front of 45/55
  • Cut and cap existing utilities at the 45/55 public sidewalk location
  • Install sediment controls at N Main catch basins and at the Jersey barriers

We look forward to the neighborhood business meeting on Monday, June 27, 2022, at 4:00 PM.