Construction activities scheduled for the next two weeks are as follows:
- Continue inside of 55 N Main with the abatement and hazmat removal work.
- Obtain a permit to close off the public sidewalk in front of 45/55 N Main
- Obtain a permit to close off three public parking spaces in N Main adjacent to 45/55
- Install Jersey concrete barriers in front of 45/55
- Install chain link temporary fence at N Main per logistics plan
- Remove the public sidewalk in front of 45/55
- Cut and cap existing utilities at the 45/55 public sidewalk location
- Install sediment controls at N Main catch basins and at the Jersey barriers