45/55 North Main Street Construction Update

Activities scheduled for the next two weeks are as follows:

  • Complete the abatement work and obtain clean air certification at both 45/55 existing buildings.
  • Remove the public sidewalk in front of both 45/55 buildings.
  • Cut and cap utilities at N Main sidewalk location.
  • Start building demolition and the hauling of debris to proper disposal sites.
  • Obtain temporary electrical power for our office trailer.