45/55 North Main Street Construction Update
Posted on: July 11, 2022 - 10:04am
Activities scheduled for the next two weeks are as follows:
- Complete the abatement work and obtain clean air certification at both 45/55 existing buildings.
- Remove the public sidewalk in front of both 45/55 buildings.
- Cut and cap utilities at N Main sidewalk location.
- Start building demolition and the hauling of debris to proper disposal sites.
- Obtain temporary electrical power for our office trailer.