From Steve King, Senior Project Manager, Groen Construction:

  • Continue with utility relocation work at the parking lot inside our staging area
  • Continue with foundation demolition work at both existing buildings 45/55 
  • Haul off site the old concrete foundation pieces 
  • Install shoring and perform remedial work adjacent to existing buildings
  • Start concrete foundations for the new building working from N Main Street towards the Union Street lot staging area