From Steve King, Senior Project Manager, Groen Construction:

  • Forms and reinforcing materials have been received 
  • Start forming and placing concrete for new building foundations
  • Continue with remedial work at Revolution rubble wall foundation
  • Start new utility work in N Main Street for building water and sewer services