45/55 North Main Street Construction Update

The following activities will be going on for our project in the month of September.

  • Complete the Eversource primary power ductbank work at Union Street parking lot and set new transformer pad for new electrical service to the building
  • Continue with building enclosure consisting of window installations at all openings
  • Continue with the exterior building synthetic stucco finishes
  • Complete parapet framing work
  • Continue with interior mechanical HVAC ducts and plumbing work
  • Continue with interior sprinkler piping roughing in work
  • Complete installation of all rooftop condensers with electrical wiring plus mechanical line set piping 
  • Continue with electrical roughing in work at unit apartments
  • Place and finish concrete slabs on grade
  • Install framing for storefront glass and finishes at N Main facade
  • Install steel stairs at interior stair towers