45/55 North Main Street Construction Update

For questions, call Matt Wyatt (603) 330-7195

From Steve King, Senior Project Manager, Groen Construction:

The following activities will be going on for our project in the month of October.

  • Continue with Eversource permanent power ductbank at Union Street lot including the transformer pad and secondary power conduits
  • Continue with EIFS synthetic stucco work at building envelope
  • Continue with interior roughing in work for MEPFP trades
  • Place and finish the interior car parking slab on grade 
  • Start interior insulation and drywall finish work from sixth floor level down
  • Continue with interior steel stair installations and railings
  • Place concrete at stair treads and landings of stair 1 at N Main
  • Remove the temporary exterior stair tower 
  • Install the five exterior windows after removal of the stair tower
  • Frame the first floor wall at N Main and install granite and precast panels for the front entrances