45/55 North Main Street Construction Update

For questions, call Matt Wyatt (603) 330-7195

From Steve King, Senior Project Manager, Groen Construction:

The following activities will be going on for our project in the month of November:

  • Complete the Eversource permanent power ductbank work at the Union Street lot including the transformer pad and secondary power conduits
  • Continue with EIFS synthetic stucco work at building envelope facade
  • Continue with interior roughing in work for MEPFP trades
  • Place and finish the interior first floor car parking slab on grade 
  • Continue with interior insulation and drywall finish work from fifth floor level down
  • Start painting sub on the sixth floor
  • Continue with interior steel stair installation at stair # 2 including railings
  • Place concrete at stair treads and landings of stair 2 
  • Continue with exterior scaffolding removal after completion of EIFS and wall caps
  • Finish framing the first floor wall at N Main and install granite and precast panels for the front entrances
  • Install overhead garage door to inside parking area
  • Receive cabinetry, flooring and interior doors and start installation work at the sixth floor