Construction Update: 45/55 North Main Street
For questions, call Matt Wyatt (603) 330-7195
Posted on: December 13, 2022 - 11:05am
From Steve King, Senior Project Manager, Groen Construction
Construction activities for the next two weeks are as follows:
- Continue with excavation work for footings and foundations
- Backfill public sidewalk area at N Main
- Remove and relocate Jersey barriers and temporary fence from N Main to public sidewalk
- Form, reinforce and place concrete at footings and ICF wall locations
- Install underground utilities within building footprint as backfill is installed in building to new slab elevations
- Backfill alley space between new building and two existing buildings
- Prepare site and staging lot for the start of steel erection