Construction Update: 45/55 North Main Street

For questions, call Matt Wyatt (603) 330-7195

From Steve King, Senior Project Manager, Groen Construction

Construction activities for the next two weeks are as follows:

  • Continue with excavation work for footings and foundations
  • Backfill public sidewalk area at N Main
  • Remove and relocate Jersey barriers and temporary fence from N Main to public sidewalk
  • Form, reinforce and place concrete at footings and ICF wall locations
  • Install underground utilities within building footprint as backfill is installed in building to new slab elevations
  • Backfill alley space between new building and two existing buildings 
  • Prepare site and staging lot for the start of steel erection