Construction Update: 45/55 North Main Street
For questions, call Matt Wyatt (603) 330-7195
Posted on: April 13, 2023 - 7:44am
From Steve King, Senior Project Manager, Groen Construction:
The construction update for the next three weeks follows:
- The third-floor slab was placed and finished today.
- Deliveries of materials for the third-floor prefab walls are set for tomorrow.
- The erection of shear walls at the two stairways starts tomorrow.
- The erection of prefab corridor walls and exterior walls starts tomorrow.
- Underground plumbing line work will commence next week inside the car parking area.
- Our work zone will be expanded to include the three car parking spaces adjacent to our new building at N Main Street.
- Placement of concrete for shear walls will occur at floor level three.
- Hambro floor joists and plywood forms will be installed for the concrete slab at level four.
- Placement of the concrete for the fourth-floor level slab is scheduled for May 02, 2023.