Construction Update: 45/55 North Main Street

For questions, call Matt Wyatt (603) 330-7195

From Steve King, Senior Project Manager, Groen Construction:

Here's an update of activities for the next four weeks:

  • Complete storm drain line work to connect building roof drains to the city storm drain in N Main.
  • Complete work for Eversource power to the building from the Union Street switch into the Union Street parking lot and set new transformer.
  • Complete secondary power lines and communication lines into the building.
  • Install EPDM roofing systems to get the building watertight at high roof and fifth-floor roof terraces.
  • Receive exterior windows and start installation with all required flashings.
  • Work on the exterior walls to install EIFS exterior finish on building envelope walls.
  • Continue with interior metal stud partition framing.
  • Continue with plumbing piping interior rough in and connections.
  • Receive fiberglass showers for installation at apartments.
  • Complete all roof drain and overflow drain piping connections.
  • Continue with HVAC condensate and line set rough in work.
  • Start work on the interior fire sprinkler system.
  • Start work on electrical rough in of the apartments.
  • Start the installation of steel stairs at two locations in the building.