45/55 North Main Street Construction Update

From Steve King, Senior Project Manager, Groen Construction.

  • Demolition of 45 N Main & 55 N Main is complete as of today.
  • The demolition equipment will be demobilized and leave our staging area by Thursday.
  • Survey and control layout work will be performed on Friday.
  • Utility relocation work will be performed in our staging area for the next two weeks as we prepare to start concrete foundation work for the new building.